There are various tasks that are involved in the construction of the park.  As the Contractors hired by the City of Gretna and the Gretna Public Schools, we will do our best to stick to the timelines laid out below. 

Park Grading, Roadway and Utilities: 

                Design work – Jan 2021 thru June 2021

                Construction work – May 2021 thru Aug 2022

 

Capehart Road Improvements:

                Design work – Feb 2021 thru Nov 2021

                Construction work – March 2022 thru Nov 2022

 

Ballfields and Passive Park: 

                Design work – March 2021 thru Dec 2021

                Construction work –   Sept 2021 thru April 2023

 

Community Recreation and Aquatics Facility: 

                Design work – Jan 2021 thru Sept 2021

                     Construction work – Sept 2021 thru May 2023